Telecommunications Switching Site
San Diego, California
This project consisted of preconstruction and construction services for a fast-track, 12,075-square-foot tenant improvement for Adelphia Business Solutions.
The project scope included demolition, installation of fiber optic conduits, interior concrete patching and new equipment pads, UPS and electrical room, installation of five 30-ton Data-Air Units 24-hour cooling systems, liquid detection system and FM-200 and pre-action fire suppression system, electrical service upgrade including a new 2000A 480 VAC service with transformers and ATS for 1200 KW stand-by generator, erection of demising walls, exterior equipment yard, new office space and ADA restroom upgrades.
Architect GBC Architects
Owner Adelphia
Office:
Swinerton Builders Critical Facilities
|
|